Coverage / ERCOT

Texas has the deepest public large-load record.

This page separates adopted deadlines, completed events, ERCOT's stated operational targets, and superseded dates. Batch Zero timing is current through 2026-08-26.

Observed record / ERCOT LLWG Report, June 2026

1.2%

Requested MW reported as observed energized.

One ERCOT report, three different measures. Requested, approved to energize, and observed energized are not interchangeable.

01
Requested
466,497 MW
02
Approved to energize
8,926 MW
03
Observed energized
5,700 MW
Primary ERCOT report ↗

June 2026 snapshot. Treat as stale until a later ERCOT LLWG report. Observed energized (5,700 MW) is not the 8,926 MW approved to energize and is not the report's 3,900 MW June monthly peak.

The Batch Zero timeline — next: Conditional-classification notices to DSP/TSP

PUCT approved the Batch Zero package

PUCT gave final approval to ERCOT's protocol package (PGRR145 / NPRR1325) on June 18, 2026. The rule is locked. The deadlines below are binding, not contingent.

Complete

ILLE submission deadline

Forms, attestations, and eligibility materials due to your interconnecting TSP/DSP, including notarized Form W Part A (PCLR) and Form X (WLPUN) where elected. Separately, the Planning Guide §9.2.2(3) study and dynamic-model data go directly from the ILLE to ERCOT at BatchZero@ercot.com by 2359 CDT, per market notice M-B062326-04. Miss it and the project is excluded from Batch Zero.

Binding

TSP/DSP qualification packages due to ERCOT

Your interconnecting TSP/DSP submits the Batch Zero interconnection details to ERCOT: the LIF workbook and, where applicable, the Dynamic Stability Study Form and §9.2.1.4(3)(d) attestation, plus the ILLE forms you filed with them by July 10, including notarized Form W Part A (PCLR) and Form X (WLPUN) where elected. Separately, an ILLE on the §9.2.1.2 eligibility path files its §9.2.1.2(1) attestation with its DSP/TSP by this same date.

Binding

QSA prerequisites for early-2027 energization

Seeking Initial Energization in January, February, or March 2027 meant satisfying all Planning Guide §5.3.5 prerequisites by this date. After this gate passed, M-A080326-01 announced ERCOT would not issue classifications by the adopted August 7 deadline and would seek a good-cause exception, which the PUCT granted on August 20, 2026.

Binding

Original classification deadline

Superseded. The August 20, 2026 PUCT order granted ERCOT's good-cause exceptions, including relief from this Planning Guide §9.3.1(2)(a) deadline. Do not present August 7 as a live commitment or as a claim that ERCOT issued no replacement timing.

Superseded

PUCT granted good-cause exceptions

The August 20, 2026 PUCT open meeting / order granted ERCOT's requested good-cause exceptions for the Batch Zero process. ERCOT restated that grant in market notice M-A080326-02 (August 21, 2026).

Complete

Conditional-classification notices to DSP/TSP

ERCOT stated it intends to notify each interconnecting DSP or TSP of each Large Load's conditional classification by August 31, 2026. That is ERCOT's own stated intent in market notice M-A080326-02, not an adopted deadline or a commitment the PUCT ordered. That notice starts dispute and reconciliation under Planning Guide §9.3.1(2)(a)(i)-(iii). August 31 is not a final classification date, a final-inclusion cut, a study-results date, or a customer filing deadline.

ERCOT target

As of August 26, 2026. August 31 starts dispute and reconciliation after conditional-classification notices, not final inclusion. Timing claims go stale when ERCOT publishes a later market notice.